Tennessee building permits

Tennessee's State Fire Marshal's Office (part of the Department of Commerce and Insurance) adopts minimum building codes. Cities and counties that run their own code programs ("exempt jurisdictions") issue their own permits. Elsewhere the state issues residential building permits, unless the county or city has opted out of the residential code. The state electrical permit and inspection program covers most of Tennessee outside a list of exempt cities and counties. Contractors need a state license for jobs of $25,000 or more, and some counties also require a home improvement license for smaller remodeling jobs.

Local profiles
95
Link an online portal
44 (46%)
County office
55
City or town offices
24
State agency
16

How permits work in Tennessee

Building codes

Partial statewide code

For one- and two-family homes and townhouses, the state residential code is the 2018 International Residential Code (IRC) with Tennessee amendments (Rule 0780-02-23-.02, last amended effective July 16, 2020). Fire sprinklers in homes are not required, and the IRC electrical chapters are replaced by the state electrical rules. Energy work follows the 2018 IECC with amendments. For other buildings, a rule effective April 17, 2025 moved the state to the 2021 IBC, IFC, IPC, IMC, IFGC, IEBC and IECC (Rule 0780-02-02). Plans could use the older codes until August 15, 2025. The state electrical code is the 2017 National Electrical Code with Tennessee exceptions, effective October 1, 2018 (Rule 0780-02-01-.02). The state's own electrical program still listed the 2017 NEC as of August 2026. Local governments may enforce their own codes, but their codes must be no more than seven years older than the latest edition. They may not weaken the state standards without the State Fire Marshal's written approval. A city or county may also opt out of the state residential code by resolution (Rule 0780-02-23-.14). Where it does, no state residential building permit is required.

Tennessee Department of Commerce and Insurance, Division of Fire Prevention (State Fire Marshal's Office)

Outside city limits

It depends on the county. Some counties run their own building department and issue permits in unincorporated areas. In counties that have neither their own program nor an opt-out, a new home or an addition of 30 sq ft or more of interior space needs a state residential building permit. The permit comes from a state-authorized issuing agent, and state deputy building inspectors do the inspections. Where the county has opted out, the unincorporated areas need no residential building permit (Rule 0780-02-23-.05). In most counties a state electrical permit is still required, and a septic system always needs a state permit.

Contractors and owner-builders

The Tennessee Board for Licensing Contractors licenses prime contractors for projects of $25,000 or more. Electrical, mechanical, plumbing, HVAC and roofing subcontractors need a license when their part of the job is $25,000 or more, and masonry subcontractors need one at $100,000 or more. In Bradley, Davidson, Hamilton, Haywood, Knox, Marion, Robertson, Rutherford and Shelby counties, a home improvement license is also required for residential remodeling jobs from $3,000 to $24,999 (T.C.A. § 62-6-501 et seq.). Property owners building a home for their own use do not need a contractor license. In the state residential program, a property owner's permit is for an owner of record building a one-family home they plan to live in. Under T.C.A. § 62-6-103, an individual may get only one property owner's permit in any 24-month period. The owner does not need to show a license, but the work gets the same inspections (Rule 0780-02-23-.01, -.05). Local building departments set their own owner-permit rules.

Tennessee Department of Commerce and Insurance, Board for Licensing Contractors · Look up a license

Electrical, plumbing, and HVAC

Electrical, plumbing and HVAC contractors are licensed by the Board for Licensing Contractors (the CE, CMC-A and CMC-C classifications) for jobs of $25,000 or more. For smaller jobs, the Board issues Limited Licensed Electrician (LLE) and Limited Licensed Plumber (LLP) licenses. These are required in places that use the State Fire Marshal's Office for permits or inspections. Plumbing maintenance work under $500 is exempt from the LLP. Cities with their own programs may have local licensing instead. The State Fire Marshal's Office runs the state electrical permit and inspection program through about 100 contracted deputy electrical inspectors, and permits are sold online through the CORE system and by local issuing agents.

State programs that can affect your permit

  • State electrical inspection program

    Outside the exempt jurisdictions, an electrical permit is required before installing wiring that must be inspected under Rule 0780-02-01-.04. Contracted deputy electrical inspectors do the inspections. The exempt jurisdictions are mostly larger cities (for example Knoxville, Chattanooga, Clarksville, Franklin and Murfreesboro), plus all of Davidson (Metro Nashville), Hamilton and Shelby counties. They run their own electrical permits.

  • State residential building permit program

    The same State Fire Marshal's section issues residential building permits and inspects new one- and two-family homes, townhouses and additions of 30 sq ft or more of interior space. It covers places that neither enforce their own residential code nor have opted out.

  • Subsurface sewage disposal (septic) permits

    Anyone installing a septic system, or repairing a failing one, needs a Septic System Construction Permit from TDEC's Division of Water Resources. Some contract counties (Blount, Davidson, Hamilton, Jefferson, Knox, Madison, Sevier, Shelby and Williamson) may require an extra local permit. A residential building permit application must certify that public sewer or a septic permit is available.

  • Manufactured housing

    The State Fire Marshal's Manufactured Housing Section licenses manufacturers, retailers and installers of HUD-labeled manufactured homes. It also inspects installations under the Tennessee Manufactured Home Installation Act. Setting a manufactured or modular home is not "construction" under the state residential code, but any added site-built construction is.

Tennessee county directory

95 local profiles

Portal links an online permit portal (44). Fees links a fee schedule (55). Profiles that point to a city, town or state agency are labeled.

A

B

C

D

F

G

H

J

K

L

M

O

P

R

S

T

U

V

W

Profiles marked “City or town offices” point to municipal permit offices because the county does not issue general building permits. Profiles marked “State agency” point to a state program that handles permits or oversight there.

Statewide rules for common projects

  • Electrical work

    In areas served by the state electrical program, a permit is required before installing wiring that must be inspected under Rule 0780-02-01-.04. A residential property owner can buy an individual-use permit for a home that is not for sale, lease or rent, and doesn't need to show a license.

    Official source · Electrical work permit guide

  • Roof replacement

    Under the state residential program, reroofing and residing count as "renovation" rather than "construction," so they don't need a state residential building permit (Rule 0780-02-23-.01). Cities and counties with their own building departments may still require a permit.

    Official source · Roof replacement permit guide

  • Decks

    Under the state residential program, decks, porches and other additions of exterior space, and additions of less than 30 sq ft of interior space, count as renovation, so no state residential building permit is needed (Rule 0780-02-23-.01). Local building departments may require one.

    Official source · Decks permit guide

Tennessee permit questions

Can I pull my own permit to build my house in Tennessee?

Yes, in most places. Under the state residential program, an owner of record building a one-family home they plan to live in can get a property owner's permit without a contractor license. You are limited to one such permit every 24 months, and all inspections still apply. In cities and counties with their own building departments, ask the local office about its rules.

Do I need an electrical permit to do my own wiring?

Usually yes. In areas covered by the state electrical program, a homeowner can buy an individual-use electrical permit for work on their own residence or farm building that is not for sale or rent, and the work must pass inspection. In exempt cities and counties, such as Nashville, Knoxville and Memphis/Shelby County, contact the local electrical office.

My county doesn't have a building department. Do I still need a permit?

Possibly. If your county has not opted out of the state residential code, a new house or an addition of 30 sq ft or more of interior space needs a state residential building permit. If the county has opted out, no building permit is needed in unincorporated areas. Electrical permits and septic permits are still required.

Do I need a licensed contractor for a remodeling job under $25,000?

A state contractor license is required only for jobs of $25,000 or more. In Bradley, Davidson, Hamilton, Haywood, Knox, Marion, Robertson, Rutherford and Shelby counties, residential remodeling from $3,000 to $24,999 requires a home improvement license. Electrical and plumbing work in state-inspected areas needs at least a limited license (LLE or LLP).

Which code edition will my new house be inspected under?

Under the state program, the 2018 IRC with Tennessee amendments and the 2017 NEC. Cities and counties with their own programs may use newer editions, but they must stay within seven years of the latest published edition. Ask your local office.

Permit guides for common projects

What the model codes say, what local offices often change and what to ask; read them with the Tennessee rules above.

Sources

Last verified October 28, 2026. State rules change. The issuing agency’s current instructions control if they differ from this summary. Suggest a correction