Quick answer
There is no national permit fee. The model code leaves the fee schedule to "the applicable governing authority" (IRC R108.2), so your county or city decides. Most offices use one of three methods: a percentage or stepped table based on the value of the work, a rate per square foot, or a flat fee for common jobs like roofs, fences and water heaters. Plan review, separate electrical, plumbing and mechanical permits, state surcharges, impact fees and reinspection fees are often extra. For a 2,000-square-foot house, the building permit alone ranges from about $500 in Columbia County, Georgia, to about $2,200 in Spalding County, Georgia, under their current schedules. Starting work without a permit usually costs more: Spalding County charges twice the calculated fee.
Who sets the fee
The International Residential Code, which most U.S. counties and cities adopt for houses, doesn’t set any dollar amounts. It says a fee for each permit “shall be paid as required, in accordance with the schedule as established by the applicable governing authority” (R108.2), and that a permit “shall not be valid until the fees prescribed by law have been paid” (R108.1). So the number comes from a local fee ordinance or resolution, and it can change every year. Some counties tie their fees to inflation. Spalding County, Georgia, says its rate table is “adjusted annually based on CPI,” and Columbia County, Oregon, raised its fees for fiscal 2025-26 by the inflation rate (2.8%).
Every county profile in our directory links the official fee schedule where the office publishes one. Find yours through the state directory or the search.
The three common ways fees are calculated
1. By the value of the work
The application asks what the work is worth, and the fee comes from a table. The IRC says valuation “shall include total value of the work for which a permit is being issued, such as electrical, gas, mechanical, plumbing equipment and other permanent systems, including materials and labor” (R108.3).
Many valuation tables follow the same stepped pattern: a base amount for the first slice of value, plus a set charge for each additional $1,000. The structural permit table in Columbia County, Oregon’s July 2025 fee notice (for fiscal 2025-26) is a typical example:
| Total valuation | Permit fee |
|---|---|
| Up to $2,000 | $143 (minimum) |
| $25,001 to $50,000 | $517 for the first $25,000, plus $13 for each additional $1,000 |
| $50,001 to $100,000 | $842 for the first $50,000, plus $10 for each additional $1,000 |
| $100,001 and up | $1,342 for the first $100,000, plus $9 for each additional $1,000 |
Under that table, a $30,000 remodel has a permit fee of $517 + (5 × $13) = $582. The county adds a plan review fee of 75% of the permit fee ($436.50), then a 12% state surcharge and a 3% technology fee.
How offices check your number. For new houses and additions, many offices don’t take the stated value at face value. They multiply the floor area by a cost per square foot from the International Code Council’s Building Valuation Data (BVD). Columbia County, Oregon, uses “the ICC Building Valuation Data Table current as of April 1 of each year.” The August 2026 BVD lists these national averages:
- One- and two-family homes (Group R-3), wood frame (type VB): $177.63 per square foot. Type VA is $189.52.
- Private garages (which use Group U, utility): $71.79 per square foot for type VB.
- Unfinished basements (R-3): $31.50 per square foot.
These are valuations used to compute a fee, not the fee itself. The ICC says the table “is not intended to be used as an estimating guide,” that it reflects national averages without regional adjustments, and that it “is not intended to apply to alterations or repairs to existing buildings.” The ICC also describes how a department can set a “Permit Fee Multiplier” from its budget and the total value of local construction. Its example multiplier is 0.0075, which works out to $0.75 per $100 of valuation.
2. By the square foot
Some counties skip valuation and charge a rate per square foot:
- Spalding County, Georgia: a rate by occupancy and construction type. For a wood-frame house (R-3, type VB) it is $1.09 per square foot, plus a $25 administrative fee on most permits. Residential renovations under $75,000 use a flat table instead, from $350 for up to 500 square feet to $575 for more than 2,000. Larger interior remodels are charged at 60% of the rate.
- Columbia County, Georgia (effective July 8, 2026): $0.25 per square foot “under roof” for a new single-family home, townhome, duplex, manufactured or modular home, ancillary dwelling or accessory structure. Additions and alterations are $250 plus $0.25 per square foot.
- Columbia County, Florida (published October 2025): for single-family homes, additions and attached garages, the square footage is multiplied by $60 to set a valuation, and the fee is $8 per $1,000 of that valuation. That works out to $0.48 per square foot.
3. Flat fees
Smaller and repetitive jobs usually have a flat fee. A few examples from the same schedules:
| Work | Columbia County, GA | Spalding County, GA |
|---|---|---|
| Roof replacement | $150 | $100 |
| Deck or porch | $150 + $0.20 per sq ft | $150 |
| Pool | $350 | $250 |
| Demolition | $80 | $100 |
| Stand-alone electrical, plumbing or mechanical permit | $75 each | $100 |
For electrical permit fees in more places, including state-run programs, see our electrical permits guide.
What gets added on top
- Plan review. Often a percentage of the permit fee. Columbia County, Florida, charges 25% of the building fee (minimum $75, maximum $25,000). Columbia County, Oregon, charges 75%. Spalding County charges no plan review fee for detached single-family homes but charges 25% for attached and multifamily homes.
- Trade permits. Electrical, plumbing, mechanical and gas work often need their own permits. Columbia County, Georgia, says its residential building fees don’t include sub-trade permits.
- State surcharges. Florida adds 1% of permit fees (F.S. 553.721) and 1.5% (F.S. 468.631), each with a $2 minimum. Virginia’s building code requires local departments to collect “a 2.0% levy of fees charged for permits” for the state’s training program (USBC 107.2), though localities that run their own accredited training academies keep it.
- Impact fees. Many fast-growing counties charge new homes for roads, schools, parks and utilities. These are set separately from the permit fee, and Florida law says impact fees can’t be collected before the building permit is issued (F.S. 163.31801). Sarasota County’s permit portal links an impact fee estimator.
- Other approvals. Zoning, septic or health department, driveway and floodplain permits come from other desks or agencies. Columbia County, Florida, lists a $150 right-of-way (driveway) permit and a $50 development permit.
- Reinspection fees. Charged when work isn’t ready or fails. Columbia County, Georgia, charges $30 for the first and $50 for each one after. Columbia County, Florida, and Spalding County charge $50. Columbia County, Oregon, charges $143.
- Renewals and reactivation. If a permit expires, reviving it costs money. Columbia County, Georgia, charges $75 to reactivate a permit. Columbia County, Florida, charges a renewal fee that drops from 100% of the permit fee when no inspections are done to 25% when three quarters are done.
Penalties for starting without a permit
The IRC lets the local government charge anyone who “commences work requiring a permit … before obtaining the necessary permits” a fee “in addition to the required permit fees” (R108.6). Local versions vary:
- Spalding County, Georgia: twice the calculated permit fee.
- Cassia County, Idaho: “a monetary penalty equal to one hundred percent (100%) of the permit or inspection fee,” on top of the standard fee.
- Columbia County, Georgia: a $500 non-compliance fee.
These are on top of the cost of opening finished work for inspection. Our guide to work done without a permit covers the rest.
The same house in three counties
Here is what the building permit alone would cost for a 2,000-square-foot, wood-frame house under the schedules above. Trade permits, impact fees, septic, driveway and utility charges are not included.
| County | How it’s calculated | Building permit |
|---|---|---|
| Columbia County, Georgia | 2,000 sq ft × $0.25 (an attached garage or covered porch adds to the area under roof) | $500 |
| Columbia County, Florida | 2,000 × $60 = $120,000 valuation; $8 per $1,000 = $960; plus 25% plan review ($240) and 2.5% state surcharges ($30) | $1,230 |
| Spalding County, Georgia | 2,000 sq ft × $1.09 + $25 administrative fee | $2,205 |
The gap is large, and it isn’t a sign that one office is overcharging. Fee schedules reflect what each department spends on plan review and inspections, and which costs a county puts in the permit fee instead of other charges.
How to estimate your permit cost
- Find the right office. City limits matter: a city fee schedule replaces the county’s inside the city.
- Open the current fee schedule and check its effective date. If it’s more than a year old, ask whether a newer one exists.
- Find the method for your project: valuation, square footage or flat fee.
- Work out the valuation honestly if it’s valuation-based. Include labor, even if you’re doing the work yourself, and all the trades.
- Add plan review, trade permits, surcharges and other approvals.
- Ask the office for an estimate. Many will calculate it from your description before you apply. Ask which fees are due at application and which at issuance, and which are refundable.
For the full permit process, see how to get a building permit.
Common mistakes
- Budgeting only the building permit and forgetting trade permits, impact fees and septic or utility charges.
- Understating the valuation. Offices compare it with their own tables and can recalculate, and a low figure can delay review.
- Using an old fee schedule. Many counties update fees every year.
- Ignoring reinspection fees. Calling for an inspection before the work is ready costs money.
- Letting a permit expire. Renewal or a new permit can cost close to the original fee.
Common questions
How much is a building permit for a new house?
It depends entirely on the local fee schedule. Under current schedules, the building permit for a 2,000-square-foot house is $500 in Columbia County, Georgia ($0.25 per square foot under roof, trade permits extra), about $1,230 in Columbia County, Florida (including plan review and state surcharges), and about $2,205 in Spalding County, Georgia ($1.09 per square foot plus a $25 administrative fee). Impact fees, utility connection fees and septic permits can add much more.
Is the permit fee based on what I pay my contractor?
Often, yes. The IRC says permit valuation 'shall include total value of the work,' including electrical, gas, mechanical, plumbing and other permanent systems, 'including materials and labor' (R108.3). Many offices check the value you state against a published table such as the ICC Building Valuation Data, and can use their own figure if yours looks low. If you do the work yourself, the office will usually still value it as if you had paid for labor.
Do I need separate electrical and plumbing permits?
In many places, yes. Columbia County, Georgia, for example, says its residential building permit fees do not include sub-trade permits, and charges $75 each for electrical (up to 400 amps), plumbing and mechanical. Some offices bundle trades into one permit for a new house. Ask before you budget.
Can I get a refund if I cancel my permit?
The IRC lets the building official set a refund policy (R108.5), so it varies. Virginia requires its local building departments to refund, on written request, the part of the fee for work not completed when a permit is revoked or abandoned (USBC 107.1.2). Application and plan review fees are often non-refundable once review has started.
What happens to the fee if I start work before getting the permit?
Expect to pay more. The IRC lets the governing authority charge a fee for work started before a permit is issued, 'in addition to the required permit fees' (R108.6). Spalding County, Georgia, charges twice the calculated permit fee, and Cassia County, Idaho, adds a penalty equal to 100% of the permit or inspection fee.
Check your county’s rules
The rules above are a starting point. Your county, city or state agency decides which rules and code edition apply, what it changed, and what it charges. Look up the permit office that serves your address.
Sources
- 2024 International Residential Code, Chapter 1 (R108 fees, R108.6 work commencing before permit issuance), unamended adoption reproduced by UpCodesup.codes
- International Code Council: Building Valuation Data, August 2026www.iccsafe.org
- Spalding County, Georgia: Building Permit Fee Schedule (Rev. 11/24)cdn.prod.website-files.com
- Columbia County, Georgia: Building Standards Fee Schedule (effective July 8, 2026)columbiacountyga.gov
- Columbia County, Florida: Building Permit Fee Schedule (published October 2025)www.columbiacountyfla.com
- Columbia County, Oregon: Notice of fee increase and fee schedule (July 2025, fiscal 2025-26)www.columbiacountyor.gov
- Cassia County, Idaho: Permit information (penalty for work without a permit)www.cassia.gov
- Florida Statutes § 553.721: Surcharge (1 percent of permit fees)www.leg.state.fl.us
- Florida Statutes § 468.631: Building Code Administrators and Inspectors Fund (1.5 percent of permit fees)www.leg.state.fl.us
- Florida Statutes § 163.31801: Impact feeswww.leg.state.fl.us
- Virginia Uniform Statewide Building Code, 13VAC5-63-70 (Section 107, fees and the 2% state levy)law.lis.virginia.gov
Last reviewed November 2026. Code section numbers such as R105.2 refer to the International Code Council’s model codes; CFR citations refer to the Code of Federal Regulations. We checked the wording against the sources linked above; code adoptions cited there reproduce the model text without amendment unless the source notes a state amendment. Codes take effect only when a state or local government adopts them, and many make amendments. This guide is general information, not legal or engineering advice. Suggest a correction