Quick answer
Communities in the National Flood Insurance Program must "require permits for all proposed construction and other developments" in mapped special flood hazard areas (44 CFR 60.3(b)(1)). Federal rules define development broadly, including "filling, grading, paving, excavation or drilling operations or storage of equipment or materials" (44 CFR 59.1), so work that needs no building permit can still need a floodplain permit. New and substantially improved homes must have the lowest floor at or above the base flood elevation (60.3(c)(2)). Improvements or repairs costing 50 percent or more of the building's market value count as substantial. Check your zone at FEMA's Flood Map Service Center (msc.fema.gov) and ask your local floodplain administrator.
Why floodplain permits exist
Floodplain permits come from the National Flood Insurance Program (NFIP). FEMA makes flood insurance available in the program’s 22,600 participating communities, and in exchange each community agrees to regulate building in its mapped flood zones. Federal rules require participating communities to “require permits for all proposed construction or other development in the community… so that it may determine whether such construction or other development is proposed within flood-prone areas” (44 CFR 60.3(a)(1)). Once FEMA maps special flood hazard areas, the community must require permits for all development within them (60.3(b)(1)).
Each community must designate “the agency or official with the responsibility, authority, and means” to carry out these rules (44 CFR 59.22(b)(1)). That person is usually called the floodplain administrator. In Texas, state law requires each city and county to adopt floodplain ordinances or orders to take part in the NFIP (Water Code §16.3145), so participating counties, including small rural ones, appoint their own floodplain administrators for unincorporated areas. Alabama’s state coordinating office puts the rule simply: “When a community chooses to participate in the NFIP, it must require permits for all development in the SFHA.”
The floodplain permit is separate from the building permit, though many offices process them together. It can be required where no building permit is needed at all.
What counts as development
The federal definition is broad: “any man-made change to improved or unimproved real estate, including but not limited to buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations or storage of equipment or materials” (44 CFR 59.1).
In a mapped flood zone, that can include:
- New homes, additions and garages.
- Substantial remodels and flood repairs (see the 50 percent rule below).
- Sheds and accessory buildings, even ones exempt from the building code. See our shed permit guide.
- Fill, grading and driveways, including bringing in dirt to raise a building pad. See our driveway and culvert guide.
- Fences and walls that could block flow, especially in a floodway. See our fence permit guide.
- Manufactured homes, which must be elevated and anchored.
- Pools, tanks and stored materials.
Check your flood zone
Start at FEMA’s Flood Map Service Center, msc.fema.gov, the official public source for NFIP flood hazard maps. Search your address and look at the Flood Insurance Rate Map (FIRM):
- Zones A, AE, AH and AO are special flood hazard areas, with a 1 percent annual chance of flooding. AE zones show a base flood elevation (BFE).
- Zones V and VE are coastal high-hazard areas with wave action.
- The regulatory floodway is the channel and nearby land that must stay open to carry flood flows. It is the most restricted area.
- Zone X areas are outside the special flood hazard area, though they can still flood.
Ask the floodplain administrator whether newer preliminary maps or local studies apply. If you believe your property is mapped in error because it sits on high ground, you can request a Letter of Map Amendment (LOMA). FEMA says “There is no review and processing fee for the FEMA review of a LOMA request,” and it normally issues a determination in 60 days. A request based on fill (LOMR-F) carries a fee.
Building rules in a flood zone
The federal minimums, which many communities exceed, include:
- Elevation. In A1-30, AE and AH zones, new and substantially improved homes must “have the lowest floor (including basement) elevated to or above the base flood level” (44 CFR 60.3(c)(2)). Some communities require one or more feet of extra height, often called freeboard.
- Floodways. Encroachments, “including fill, new construction, substantial improvements, and other development,” are prohibited unless an engineering analysis shows they “would not result in any increase in flood levels” during the base flood (60.3(d)(3)).
- Coastal V zones. Homes must be on pilings or columns with the bottom of the lowest horizontal structural member at or above the base flood level, certified by an engineer or architect, and the area below must be open or enclosed only with breakaway walls (60.3(e)).
The 50 percent rule
Federal rules define substantial improvement as “any reconstruction, rehabilitation, addition, or other improvement of a structure, the cost of which equals or exceeds 50 percent of the market value of the structure before the ‘start of construction’ of the improvement.” Substantial damage is damage “of any origin” where restoring the building would cost 50 percent or more of its pre-damage market value (44 CFR 59.1).
If a project crosses the line, the whole building must be brought into compliance, which in most A zones means elevating it to or above the BFE. Things to know:
- Market value is the building only, not the land. Communities may accept a tax assessment, an appraisal or another method.
- The cost includes the whole project. A kitchen, bath and roof done together count together.
- Two exclusions in the federal definition: work to correct identified code violations, and alterations to a historic structure that keep its historic designation.
- Stricter local rules are common. FEMA notes that some communities adopt a lower threshold, “such as 40 percent or 30 percent,” or track improvements over a period of years, called cumulative substantial improvement.
After a flood, the floodplain administrator decides which damaged buildings are substantially damaged, often using FEMA’s Substantial Damage Estimator. Don’t start repairs before that determination. If you have NFIP flood insurance, Increased Cost of Compliance coverage pays up to $30,000 toward elevating, relocating, floodproofing or demolishing a substantially damaged building. FEMA’s Substantial Improvement/Substantial Damage Desk Reference (P-758) explains how communities apply the rule.
Elevation certificates
For new and substantially improved buildings where a BFE is available, the community must obtain the lowest-floor elevation and keep the record (44 CFR 60.3(b)(5)). The standard document is FEMA’s Elevation Certificate, Form FF-206-FY-22-152. It is completed by “a land surveyor, engineer, or architect who is authorized by state law to certify elevation information.”
Many communities ask for one certificate based on construction drawings, another once the lowest floor is set, and a final one at completion. A completed certificate does not expire “unless there is a physical change to the building.” The same certificate is used to rate flood insurance, so keep a copy. If you are buying a home, the Texas Water Development Board’s advice applies widely: the state does not keep elevation certificates on file, “however, your local floodplain administrator should.”
Permits and inspections you can expect
- Pre-application call to the floodplain administrator to confirm the zone, BFE, floodway status and any local freeboard.
- Floodplain development permit application with a site plan showing the flood zone boundary, proposed elevations and fill.
- Elevation certificate based on drawings, if requested.
- Elevation check when the lowest floor or foundation is set, before construction continues.
- Final elevation certificate and inspection before the certificate of occupancy.
What to prepare
- FIRM panel number and zone, printed from msc.fema.gov.
- Site plan showing structures, fill, the flood zone line and the floodway.
- Elevations from a surveyor: existing grade, proposed lowest floor and the BFE.
- For remodels and repairs: an itemized cost estimate and the building’s market value, so the 50 percent test can be run.
- For floodway work: an engineer’s no-rise analysis.
Common mistakes
- Assuming no building permit means no floodplain permit. Fill, grading and small sheds can all count as development.
- Splitting a remodel into phases. Communities that track cumulative improvements add the phases together.
- Starting flood repairs before the substantial damage determination.
- Valuing the land with the house when estimating the 50 percent test.
- Relying on an old map. Check the current FIRM and ask about preliminary maps.
- Skipping the elevation check before framing, when a floor that is too low is still cheap to fix.
If you are unsure whether earlier work was permitted, our guides to searching permit records and unpermitted work can help. To find your county or city office, browse by state.
Common questions
Who is my local floodplain administrator?
Each community in the National Flood Insurance Program must designate an agency or official to carry out its floodplain rules (44 CFR 59.22). The job title is usually floodplain administrator or floodplain manager, and the role is often held by the county engineer, building official, planning director or emergency manager. In unincorporated areas it is usually a county official; inside city limits it is the city. Call the county or city permit office and ask who handles floodplain permits.
How do I find out if my property is in a flood zone?
Search your address on FEMA's Flood Map Service Center at msc.fema.gov, the official public source for National Flood Insurance Program flood hazard maps. Zones beginning with A or V are special flood hazard areas. Your local floodplain administrator may have newer or more detailed maps, so confirm with them before you design.
What is the 50 percent rule?
Federal rules treat any reconstruction, rehabilitation, addition or other improvement costing 50 percent or more of the structure's pre-project market value as a substantial improvement. Repairing damage of any origin that would cost 50 percent or more of the pre-damage market value is substantial damage. Either way, the building must then meet the floodplain rules for new construction, which usually means elevating it.
Do I need an elevation certificate?
For new construction and substantial improvements in a special flood hazard area, the community must obtain and keep a record of the lowest floor elevation, and an elevation certificate is the standard way to document it. It is completed by a land surveyor, engineer or architect authorized by state law. A completed certificate does not expire unless the building is physically changed.
Can I get my property removed from the flood zone?
If your lot or house is on naturally high ground that the map does not show, you can ask FEMA for a Letter of Map Amendment (LOMA). FEMA does not charge a review fee for LOMA requests and normally issues a determination in 60 days. If the ground was raised with fill, the request is a LOMR-F, which does have a fee.
Check your county’s rules
The rules above are a starting point. Your county, city or state agency decides which rules and code edition apply, what it changed, and what it charges. Look up the permit office that serves your address.
Sources
- 44 CFR 60.3: Flood plain management criteria for flood-prone areas (eCFR)www.ecfr.gov
- 44 CFR 59.1: Definitions (development, substantial improvement, substantial damage) (eCFR)www.ecfr.gov
- 44 CFR 59.22: Prerequisites for the sale of flood insurance (eCFR)www.ecfr.gov
- FEMA Flood Map Service Centermsc.fema.gov
- FEMA P-758: Substantial Improvement/Substantial Damage Desk Referencewww.fema.gov
- FEMA: Substantial Damage Estimator toolwww.fema.gov
- FEMA P-213: Answers to Questions About Substantially Improved/Substantially Damaged Buildings (2018)www.fema.gov
- FEMA Elevation Certificate, Form FF-206-FY-22-152www.fema.gov
- FEMA: Letter of Map Amendment and Letter of Map Revision Based on Fillwww.fema.gov
- FEMA: Flood insurancewww.fema.gov
- FEMA: Increased Cost of Compliance coveragewww.fema.gov
- Texas Water Development Board: National Flood Insurance Programwww.twdb.texas.gov
- Alabama Department of Economic and Community Affairs: Floods frequently asked questionsadeca.alabama.gov
Last reviewed November 2026. Code section numbers such as R105.2 refer to the International Code Council’s model codes; CFR citations refer to the Code of Federal Regulations. We checked the wording against the sources linked above; code adoptions cited there reproduce the model text without amendment unless the source notes a state amendment. Codes take effect only when a state or local government adopts them, and many make amendments. This guide is general information, not legal or engineering advice. Suggest a correction