Quick answer
Under the model code, the building official can order work stopped (IRC R114), issue a notice of violation, and pursue penalties set by local law (R113). The usual outcome is an after-the-fact permit at a higher fee: the IRC lets local governments add a fee for work started before a permit was issued (R108.6), and many charge double. Spalding County, Georgia, charges twice the calculated permit fee, and Cassia County, Idaho, adds a 100% penalty. To legalize the work you'll typically submit plans of what was built, open walls or ceilings so the inspector can see the framing, wiring and plumbing, and fix anything that doesn't meet code. If the work can't be approved, it has to be removed. When you sell, known unpermitted work generally has to be disclosed.
What the code lets the building official do
Most counties and cities adopt the International Residential Code’s enforcement chapter with local changes. Under the 2024 IRC:
- It’s a violation. “It shall be unlawful for any person, firm or corporation to erect, construct, alter, extend, repair, move, remove, demolish or occupy any building, structure or equipment regulated by this code” in conflict with it (R113.1).
- Notice of violation. The building official “is authorized to serve a notice of violation or order on the person responsible” (R113.2). If it isn’t complied with in the time given, the building official can ask the jurisdiction’s legal counsel to start proceedings (R113.3), and violators are “subject to penalties as prescribed by law” (R113.4). The penalty amounts are in local ordinances, not the IRC.
- Stop-work order. Where work is being done contrary to the code or “in a dangerous or unsafe manner,” the building official can issue a written stop-work order, and “the cited work shall immediately cease” (R114.1, R114.2). Anyone who keeps working “shall be subject to fines established by the authority having jurisdiction” (R114.4).
- Utilities. A utility, fuel, water or sewer connection to work that needs a permit can’t be made “until approved by the building official” (R111.1). Unpermitted work on a new building or service can hold up power or gas.
- Right of entry. The building official can enter “at all reasonable times” to inspect where there is reasonable cause to believe a violation exists. If entry is refused, the official “shall have recourse to every remedy provided by law to secure entry,” which usually means a warrant (R104.4).
Fees and fines
The IRC lets the local government charge anyone who starts work before getting a permit “a fee established by the applicable governing authority that shall be in addition to the required permit fees” (R108.6). Real examples:
| Jurisdiction | Penalty for work without a permit |
|---|---|
| Spalding County, Georgia | Twice the calculated permit fee |
| Cassia County, Idaho | “a monetary penalty equal to one hundred percent (100%) of the permit or inspection fee,” on top of the standard fee |
| Columbia County, Georgia | $500 non-compliance fee |
| Montmorency County, Michigan (electrical) | $100 “work without permit” fee, plus the normal permit fees |
Some offices add investigation fees, daily fines for continuing violations, or court penalties if a notice isn’t resolved. Each county profile in our directory includes what the office publishes about work without a permit. Find yours through the state directory or the search. For how regular fees are calculated, see building permit costs.
How unpermitted work usually comes to light
- Complaints from neighbors, often about visible work like additions, decks, fences or sheds.
- Inspectors driving by active job sites, dumpsters and work crews.
- Later permit applications. When you apply for a new project, the reviewer may compare the house with earlier permits and the assessor’s record.
- Assessor updates from aerial imagery or field visits that find new square footage.
- Home sales, through disclosure forms, buyers’ inspections, appraisals and permit searches. See looking up permit records.
- Insurance claims and utility work after a fire, flood or service upgrade.
Legalizing the work: the after-the-fact permit
The usual path is to permit the work as if it were new, with the extra fee. The steps:
- Talk to the permit office first. Ask how it handles after-the-fact permits, what drawings it wants, and which inspections it will need. Some offices have a specific form or process for existing unpermitted work.
- Document what was built. Prepare as-built drawings: floor plan, framing sizes and spacing, beam and header sizes, foundation, and the electrical, plumbing and mechanical layout. Photos taken during construction help a lot.
- Check zoning. An addition or accessory building that violates a setback may need a variance, or may not be approvable at all.
- Apply and pay the permit fee plus any penalty.
- Open up the work. The code requires each stage to be approved before it’s covered: work “shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the building official,” and noncompliant work can’t be “covered or concealed until authorized” (R109.4). For finished work, the inspector will usually ask you to remove drywall or ceiling panels in specific spots so they can see framing, wiring, plumbing, insulation and connections. Some offices accept an engineer’s report for structural items instead of full exposure.
- Correct deficiencies. Expect to fix anything that doesn’t meet the code now in force, which may be newer than the code in effect when the work was done. Common corrections: GFCI and AFCI protection, smoke and carbon monoxide alarms, egress windows in basement bedrooms, guards and stairs, and venting.
- Pass the final and keep the paperwork.
Hire licensed contractors for the trade corrections where your state requires them. In Michigan, for example, the State Construction Code Act (MCL 125.1523a) sets civil fines for conspiring to get around licensing requirements on residential work.
When removal is the answer
Sometimes legalizing costs more than undoing the work, or the work can’t be approved: a structure in a setback with no variance available, a garage conversion without required parking, or a basement bedroom that can’t get an egress window. Then the options are:
- Remove the work and restore the original condition. Demolition and the trade work to disconnect systems may need their own permits.
- Change the use. A room that can’t be a legal bedroom may be approvable as a den or storage room.
- Modify the work until it can be approved, such as cutting a deck back from the property line.
Selling a house with unpermitted work
Many states require sellers to disclose problems they know about, and some forms ask about permits directly. Texas’s seller’s disclosure notice asks whether the seller is aware of “room additions, structural modifications, or other alterations or repairs made without necessary permits or not in compliance with building codes in effect at that time.” Failing to disclose work you knew about can expose you to claims after the sale.
Options for sellers:
- Legalize before listing. This gives buyers the cleanest record and avoids a last-minute renegotiation.
- Disclose and price it in, offering a credit or selling as-is.
- Close out open permits. An open or expired permit for work that was actually finished often just needs a final inspection, sometimes with a renewal fee.
Insurance
Policies differ, so ask your insurer and read your policy. Two issues come up:
- Claims involving the work. If unpermitted work caused or contributed to a loss, such as a fire traced to amateur wiring, expect questions about it during the claim.
- Rebuilding to code. After a loss, repairs must meet the current code, including parts of the house that were never permitted. Standard policies often limit the extra cost of meeting current codes. Florida, for example, treats a homeowner’s policy as including “law and ordinance” coverage limited to 25% of the dwelling limit, with 50% available as an option, unless the policyholder rejects it in writing (F.S. 627.7011).
Common mistakes
- Ignoring a stop-work order. Continuing adds fines and almost never ends well.
- Covering more work while the permit is pending. Each layer you close makes the inspection more expensive.
- Assuming old work is “grandfathered.” Work that was legal when built, under the permit rules of the time, is generally allowed to stay. Work that needed a permit and never got one usually isn’t.
- Hoping a buyer won’t notice. Permit records and assessor data are public, and many buyers check. See how to get a building permit for doing it right on the next project.
Common questions
Can I get a permit after the work is done?
Usually, yes. Most offices issue after-the-fact (sometimes called as-built or retroactive) permits. You apply as you would for new work, pay the regular fee plus any penalty, and the inspector checks the work. Concealed work often has to be uncovered for inspection, and anything that doesn't meet the code must be corrected.
How much is the fine for building without a permit?
It's set locally. The most common penalty is a multiple of the normal permit fee: Spalding County, Georgia, charges twice the calculated fee; Cassia County, Idaho, adds a penalty equal to 100% of the permit or inspection fee; Columbia County, Georgia, lists a $500 non-compliance fee. Continuing work after a stop-work order can bring separate fines (IRC R114.4). Each county profile in our directory summarizes the penalty the office publishes.
Do I have to disclose unpermitted work when I sell my house?
In many states, yes, if you know about it. Texas's seller's disclosure notice asks directly whether the seller is aware of 'room additions, structural modifications, or other alterations or repairs made without necessary permits or not in compliance with building codes in effect at that time.' Other states' forms ask similar questions or require disclosure of known material defects. Ask a real estate attorney or agent in your state.
Will my homeowners insurance cover unpermitted work?
Read your policy and ask your insurer. Unpermitted work can lead to questions during a claim, especially if it contributed to the loss. A separate issue is the cost of rebuilding to current code after a loss, which standard policies often limit; Florida, for example, treats a homeowner's policy as including law and ordinance coverage of 25% of the dwelling limit unless the policyholder rejects it in writing, with 50% available (F.S. 627.7011).
I bought a house with unpermitted work. Am I responsible?
Building code violations generally run with the property, so the current owner is usually the one the office asks to correct them, even if a previous owner did the work. If the seller didn't disclose work they knew about, you may have a claim against them; talk to an attorney. To fix the work itself, the after-the-fact permit process is the same.
Check your county’s rules
The rules above are a starting point. Your county, city or state agency decides which rules and code edition apply, what it changed, and what it charges. Look up the permit office that serves your address.
Sources
- 2024 International Residential Code, Chapter 1 (R104.4 right of entry, R108.6, R109.4, R111.1, R113 violations, R114 stop work order), unamended adoption reproduced by UpCodesup.codes
- Spalding County, Georgia: Building Permit Fee Schedule (Rev. 11/24)cdn.prod.website-files.com
- Cassia County, Idaho: Permit information (County Code 11-1-4 C penalty)www.cassia.gov
- Columbia County, Georgia: Building Standards Fee Schedule (effective July 8, 2026)columbiacountyga.gov
- Montmorency County, Michigan: Electrical permit application and fee schedule (Revised 2026)www.montcounty.org
- Texas Real Estate Commission: Seller's Disclosure Notice, form OP-H (Texas Property Code § 5.008)www.trec.texas.gov
- Florida Statutes § 627.7011: Homeowners' policies; offer of replacement cost coverage and law and ordinance coveragewww.leg.state.fl.us
Last reviewed November 2026. Code section numbers such as R105.2 refer to the International Code Council’s model codes; CFR citations refer to the Code of Federal Regulations. We checked the wording against the sources linked above; code adoptions cited there reproduce the model text without amendment unless the source notes a state amendment. Codes take effect only when a state or local government adopts them, and many make amendments. This guide is general information, not legal or engineering advice. Suggest a correction