Quick answer

The 2024 International Residential Code requires a permit for anyone who intends to "demolish" a building or structure (R105.1), and demolition is not on the list of exempt work. Utilities have to be disconnected and capped before the building comes down, usually with sign-offs from the electric, gas, water and sewer providers. The federal asbestos rule (40 CFR Part 61, Subpart M) generally does not cover an isolated house with four or fewer units, but it does cover larger buildings and multiple houses demolished as one project, and some state and local air agencies require an asbestos survey for every house. In a local historic district, expect design review or a demolition delay before a permit is issued.

What the model code says

The International Residential Code (IRC) applies to the “removal and demolition of detached one- and two-family dwellings” and townhouses (R101.2). Its permit rule covers any owner who intends to “construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure” (R105.1). Demolition is not on the list of work exempt from permit (R105.2). For a demolition application, the IRC says “the site plan shall show construction to be demolished” (R106.2).

The International Building Code (IBC), which many jurisdictions also apply to demolition, adds specific rules in Section 3303:

  • “Construction documents and a schedule for demolition shall be submitted where required by the building official” (3303.1).
  • “Service utility connections shall be discontinued and capped in accordance with the approved rules and the requirements of the applicable governing authority” (3303.6).
  • When a building is removed, the lot “shall be filled and maintained to the existing grade” or protected against hazards (3303.4).

Local codes often add their own requirements, such as erosion control, notice to neighbors, or a deadline to clear debris. Some exempt small accessory buildings that never needed a permit to build. Ask your office before you assume a garage or shed teardown is exempt.

Utilities first

Many demolition permit offices will not issue a permit, or will not let work start, until utilities are safely cut off. A typical sequence:

  1. Electric. The utility disconnects service and removes the meter. Solar panels and batteries need to be shut down and removed separately.
  2. Gas. The gas company shuts off and removes the meter and caps the service line. Propane suppliers remove tanks.
  3. Water. The water utility shuts off service at the meter or curb stop. A well may need to be capped or abandoned under state rules.
  4. Sewer. The sewer lateral is capped at the property line or main. Some cities require an inspection of the cap before backfill. Our plumbing permit guide covers sewer work.
  5. Septic. Tanks are usually pumped and then removed or filled under health department rules. See our septic permit guide.

Ask each utility for a written release or confirmation, because the permit office may ask to see it. Before excavating foundations or footings, contact 811 to have underground lines marked.

Asbestos

The federal asbestos rule, the National Emission Standard for Hazardous Air Pollutants (NESHAP) for asbestos at 40 CFR Part 61, Subpart M, covers demolition and renovation of a “facility.” The definition of facility excludes “residential buildings having four or fewer dwelling units” (40 CFR 61.141).

EPA has explained what that means in practice: “the demolition or renovation of an isolated small residential building by any entity is not covered by the asbestos NESHAP.” The rule does apply where “multiple (more than one) small residential buildings on the same site” are demolished by the same owner or operator, or where a home is demolished “as part of a larger project,” such as “an urban renewal project, a highway construction project” (60 FR 38725, 1995).

For demolitions that are covered, such as an apartment building, commercial building or several houses on one site, the owner or operator must:

  • Inspect first. “Prior to the commencement of the demolition or renovation, thoroughly inspect the affected facility” for asbestos (61.145(a)).
  • Notify the agency. Notice is required “10 working days before demolition begins,” even if no asbestos is found (61.145(a)(2) and (b)(3)(i)). Notice goes to EPA or to the state or local agency that runs the program.
  • Remove regulated asbestos before demolition, following the work-practice standards.

Even where the federal rule does not apply, state and local rules may. The Puget Sound Clean Air Agency in Washington requires that “Surveys must be conducted by an AHERA-certified building inspector” before a house is demolished, and says “You must wait 10 days after submitting an Asbestos/Demolition Notification to demolish your house,” “whether or not there is an asbestos project involved.” Landfills may also ask for an asbestos survey before accepting debris. Asbestos was used in older siding, roofing, flooring, insulation and joint compound, so an older home is worth testing before it comes down even where no survey is required.

Lead paint

EPA’s lead Renovation, Repair and Painting (RRP) rule “does not apply to demolitions of an entire free-standing building or structure.” It does apply to partial demolition, since renovation includes “the removal of building components (e.g., walls, ceilings, plumbing, windows),” when a contractor does that work for pay in housing built before 1978. See our remodel permit guide.

Historic districts and demolition delay

Historic review is local. The National Park Service says: “Under Federal Law, the listing of a property in the National Register places no restrictions on what a non-federal owner may do with their property up to and including destruction, unless the property is involved in a project that receives Federal assistance.” State and local preservation laws are another matter.

  • Local historic districts and landmarks. A historic preservation commission usually has to approve demolition, often by issuing a certificate of appropriateness, before the building department will issue the permit.
  • Demolition delay ordinances. Some cities impose a waiting period to consider alternatives even outside historic districts. Boston’s Article 85 applies to buildings in certain districts and to other buildings “at least 50 years of age,” with “a waiting period to consider alternatives.”
  • State limits. Florida, for example, does not allow local rules to stop the owner of a single-family home in a coastal high-hazard area, moderate flood zone or special flood hazard area from getting a demolition permit if the lowest finished floor is at or below base flood elevation, with exceptions for homes on the National Register and certain locally designated historic homes (Fla. Stat. §553.79(25)).

If the property is in a flood zone, tearing down and rebuilding also brings in the floodplain rules. See our floodplain permit guide.

Partial and interior demolition

Interior demolition is usually part of a remodel or alteration permit, not a separate demolition permit. The IRC’s ordinary-repair allowance excludes “the cutting away of any wall, partition or portion thereof, the removal or cutting of any structural beam or load-bearing support” (R105.2.2), so taking out walls generally needs a permit. Some cities offer an interior demolition permit so you can open walls before remodel plans are approved, which helps when you need to see framing or wiring first. Removing a load-bearing wall needs a design for the new beam and supports. Removing finishes such as cabinets, flooring and countertops on their own usually does not need a permit.

Permits and inspections you can expect

  1. Application with a site plan showing the buildings to be removed, the lot lines and anything that will stay.
  2. Utility releases and, where required, asbestos survey results or a state notification receipt.
  3. Historic or zoning sign-off in districts that require it.
  4. Sewer cap inspection before backfill, where the city requires one.
  5. Final inspection to confirm the lot is cleared, filled to grade and stabilized.

What to prepare

  • Parcel number and site plan marking every building to be removed.
  • Utility account information and contact numbers for each provider.
  • Asbestos survey if your state, air agency or landfill requires one.
  • Contractor information, including any required demolition or asbestos abatement license.
  • Debris plan: where waste will go and whether materials will be recycled.
  • Replacement plans, if you are rebuilding, since some offices review both together.

How fees work

Demolition permits are commonly a flat fee or a fee based on the building’s floor area, with separate charges for sewer cap inspections or historic review. Utilities may charge to remove meters or abandon a service line. Check the fee schedule linked from your county’s profile in our directory, and see our guide to building permit costs.

Common mistakes

  • Starting before utilities are cut off. Live gas and electric lines are the main hazard on a demolition site.
  • Assuming asbestos rules never apply to houses. State and local rules, and the federal rule for multi-house projects, can require surveys and notice.
  • Missing historic review. A local district can delay or deny demolition, and demolishing without approval can bring penalties.
  • Knocking out walls during a remodel without checking whether they are load-bearing or contain plumbing, wiring or ducts.
  • Leaving the lot open. Basements and foundation holes need to be filled to grade.
  • Forgetting the records. Keep the final inspection. A demolished building can still appear in tax or permit records until the office updates them. Our guide to searching permit records explains how to check.

State notes

Some states set a rule for this project statewide. These notes come from our state research; your city or county may add its own requirements.

Florida
Local governments may not stop the owner of a single-family home in a coastal high-hazard area, moderate flood zone or special flood hazard area from getting a demolition permit if the lowest floor is at or below base flood elevation. Such applications get only administrative code review, with no extra local hearings. Homes on the National Register and certain locally designated historic homes are excluded. Source

Common questions

Do I need a permit to tear down a shed or garage?

Usually, if the building is large enough to have needed a permit to build. The model IRC requires a permit to demolish a building or structure and has no demolition exemption. Some local codes skip the permit for small accessory buildings that were exempt to begin with. Ask your permit office, and remember utility lines to the garage still need to be disconnected safely.

Do I need an asbestos survey to demolish my house?

Under the federal rule, an isolated single-family house is generally not covered, so there is no federal survey or notice requirement. Many state and local agencies are stricter. The Puget Sound Clean Air Agency in Washington, for example, requires a survey by an AHERA-certified building inspector and a 10-day wait after notification before any house is demolished, whether or not asbestos is found. Ask your state environmental or air quality agency.

Does gutting a kitchen or bathroom need a demolition permit?

Interior demolition is usually covered by the remodel permit rather than a separate demolition permit. The IRC's repair allowance does not include cutting away walls or removing structural members, so removing walls generally needs a permit. Some cities issue separate interior demolition permits so work can start before remodel plans are approved.

Can a historic district stop me from demolishing my house?

A local historic district can require approval or impose a waiting period before demolition. National Register listing alone does not. The National Park Service says listing places no restrictions on what a non-federal owner may do with their property, including destruction, unless the project involves federal assistance or state or local preservation laws apply.

What has to happen with utilities before demolition?

Electric and gas service must be disconnected by the utilities, water service shut off, and the sewer line capped, sometimes with an inspection of the cap. The International Building Code says service connections shall be discontinued and capped under the rules of the governing authority. A septic system on the property may need to be abandoned under health department rules.

Check your county’s rules

The rules above are a starting point. Your county, city or state agency decides which rules and code edition apply, what it changed, and what it charges. Look up the permit office that serves your address.

Sources

Last reviewed November 2026. Code section numbers such as R105.2 refer to the International Code Council’s model codes; CFR citations refer to the Code of Federal Regulations. We checked the wording against the sources linked above; code adoptions cited there reproduce the model text without amendment unless the source notes a state amendment. Codes take effect only when a state or local government adopts them, and many make amendments. This guide is general information, not legal or engineering advice. Suggest a correction