Quick answer

A driveway permit, also called an access, entrance, encroachment or right-of-way permit, comes from the government that owns the road, not necessarily your building department. State highways go through the state DOT district office (TxDOT uses Form 1058, Permit to Construct Access Driveway Facilities on Highway Right of Way). County roads go through the county road, public works or engineering department, which usually sets the culvert size and inspects the pipe before backfill. Houston County, Georgia, for example, says "A permit is required prior to performing any type of work within the right of way." Contact 811 before you dig.

Who issues the permit

Driveways and culverts are not building-code items. The International Residential Code covers the house; the connection to a public road is controlled by whoever owns that road, under its own access or encroachment rules. That is why the office you need may be a road department, a public works department or a state DOT district, rather than the building department listed for your county.

  • State highways. State DOTs issue driveway or access permits through district offices. In Texas, the applicant contacts the local TxDOT district office and submits Form 1058, “Permit to Construct Access Driveway Facilities on Highway Right of Way,” and no work may begin “until a fully executed driveway permit has been received… and the applicant has given 24-hour notification to TxDOT.” The Alabama DOT issues access permits for “constructing accesses (driveways/turnouts and median crossovers) from private property to State highways.” The Georgia DOT’s rules are in its Regulations for Driveway and Encroachment Control.
  • County roads. Usually the county road department, public works, highway department or county engineer. In some rural counties the county commission or a road commissioner handles requests directly.
  • City streets. The city’s engineering, public works or streets department.
  • Private roads. No public permit for the connection, though a road association or HOA may have rules and the building permit may still review the site plan.

A road’s route number, a county GIS map or a call to the county road department will tell you who owns it. On a corner lot, the two roads may have different owners.

What the permit covers

A driveway permit typically controls the part of the driveway inside the public right-of-way: the apron where it meets the pavement, the pipe under it in the roadside ditch, and the shape of the ditch around it. Review usually covers:

  • Location and spacing. Distance from intersections and other driveways, and sight distance so drivers can see oncoming traffic.
  • Width and turning radius, and whether a paved apron is required where the driveway meets the road.
  • Drainage. The culvert size, the slope of the driveway so water does not run onto the road, and the ditch grade.
  • Materials. Pipe type, end treatments, and the apron surface.

The permit is often required for widening, paving or relocating an existing driveway, not only for a new one. Houston County, Georgia, puts it broadly: “A permit is required prior to performing any type of work within the right of way.”

Culvert size, installation and maintenance

The culvert under a driveway carries the roadside ditch. If it is too small, water backs up onto the road or a neighbor’s property, so road agencies set the size rather than leaving it to the owner. Published county examples show the range:

  • Columbia County, Georgia: “The minimum pipe size shall be 18″ within the RIGHT-OF-WAY,” in reinforced concrete or HDPE, with 24 business hours’ notice to the county before work starts.
  • Houston County, Georgia: “The type material, diameter, and length of pipe will be determined by the county,” with a minimum length of 30 feet. The pipe is inspected before backfill, and the owner or their agent “shall accomplish the installation at his/her expense.”
  • Butts County, Georgia: the inspector sets the pipe diameter, Public Works has 48 hours to inspect, and the owner maintains the pipe and driveway.

Do not assume your county works the same way. Ask who buys the pipe, who installs it, who inspects it, and who maintains it later. Columbia County, for example, says it “will not be responsible for the maintenance of pipes or culverts that are installed under private driveways.”

Where a driveway crosses a stream, rather than a roadside ditch, the culvert may also need floodplain or environmental review. See our floodplain permit guide.

Utility work and other work in the right-of-way

The right-of-way often extends well past the edge of the pavement, so work that looks like it is in your front yard may be on public land. Common projects that need a right-of-way, encroachment or utility permit include:

  • Water, sewer, gas or electric lines crossing or running along the road, such as a water service from a main on the other side of the street. The utility tap itself usually needs its own permit. See our plumbing permit guide.
  • Boring under the road for a private line or irrigation.
  • Walls, fences, gates and landscaping in the right-of-way, which some agencies prohibit or allow only by permit. Our fence permit guide covers the property-line side.
  • Regrading or filling the ditch.

On federal-aid highways, the rules are stricter. Federal regulations require states to regulate utilities in the highway right-of-way “through the establishment and enforcement of reasonably uniform policies and procedures for utility accommodation” (23 CFR 645.209).

Mailboxes. These usually do not need a permit but should be breakaway. USPS, citing federal highway guidance, says “The best mailbox supports are stable but bend or fall away if a car hits them.” It recommends a 4-by-4 wood post or a 2-inch steel or aluminum pipe buried no more than 24 inches, with the box 41 to 45 inches above the road surface and 6 to 8 inches back from the curb.

Call 811 first. 811 is “the free national before-you-dig service.” State law sets the notice period. In Texas, notice must be given no earlier than the 14th day and no later than “the 48th hour before the time the excavation is to begin, excluding Saturdays, Sundays, and legal holidays.” Alabama 811 asks for “at least 2-10 full working days.”

Permits and inspections you can expect

  1. Application with a site sketch showing the driveway location, width, distance to the nearest intersection and driveways, and the ditch.
  2. Site review. An inspector may visit to check sight distance and set the culvert size and elevation.
  3. Pipe inspection after the culvert is set and before it is covered.
  4. Final inspection after the apron and backfill are done.

On a new house, the building department may ask for the driveway permit before it issues the building permit or certificate of occupancy. Our guide to getting a building permit explains how those approvals fit together.

What to prepare

  • Parcel number and a site plan or plat showing the road, the right-of-way line, and the proposed driveway.
  • Road name and number, so the office can confirm it owns the road.
  • Driveway width, surface and use, such as a single-family home, farm field entrance or business.
  • Contractor information if someone else is setting the pipe or pouring the apron.
  • Utility locate ticket number from 811 if you are digging.

How fees work

Driveway permit fees are often modest flat fees. Houston County and Butts County, Georgia, each list $50. The permit fee is usually small next to the cost of the pipe, gravel or concrete, and labor, which fall on the owner in the county examples above. Check the road agency’s current form, and see our guide to building permit costs for how other fees are set.

Common mistakes

  • Applying to the wrong agency. A state highway through your county is not a county road.
  • Buying pipe before asking. The county may require a larger diameter, a longer length or a specific material.
  • Backfilling before the inspection. The inspector needs to see the pipe’s size, slope and bedding.
  • Assuming the yard ends at the pavement. The right-of-way line is often several feet back.
  • Ignoring sight distance. A driveway on a hill crest or curve may need to move.
  • Skipping 811. Utility lines often run in the roadside right-of-way.

Common questions

Who do I contact for a driveway permit?

The owner of the road. For a state highway, it is the state DOT district or area office. For a county road, it is usually the county road department, public works, or county engineer. For a city street, it is the city's engineering or public works department. If you are not sure who owns the road, your county's road department or GIS map can usually tell you.

What size culvert do I need under my driveway?

The road agency decides. Columbia County, Georgia, sets a minimum of 18 inches within the right-of-way. Houston County, Georgia, says the county determines the material, diameter and length, with a minimum length of 30 feet. In Butts County, Georgia, the inspector sets the diameter. Ask before you buy pipe.

Who pays for and maintains the driveway culvert?

Often the property owner. Houston County, Georgia, says the owner or their agent installs it at their own expense. Columbia County, Georgia, says it will not maintain pipes or culverts installed under private driveways, and Butts County, Georgia, makes the owner responsible for maintaining the pipe and driveway. Practices vary, so ask your county.

Do I need a permit to work in the right-of-way in front of my house?

Often yes. The public right-of-way usually extends past the pavement and ditch onto what looks like your front yard. Digging for a utility line, building a wall, regrading the ditch, or widening a driveway in that strip commonly needs a right-of-way or encroachment permit from the road owner.

How much notice do I need to give 811?

It depends on the state. Texas law requires notice no later than the 48th hour before excavation begins, excluding weekends and legal holidays, and no earlier than the 14th day before. Alabama 811 asks for at least 2 to 10 full working days. 811 is free.

Check your county’s rules

The rules above are a starting point. Your county, city or state agency decides which rules and code edition apply, what it changed, and what it charges. Look up the permit office that serves your address.

Sources

Last reviewed November 2026. Code section numbers such as R105.2 refer to the International Code Council’s model codes; CFR citations refer to the Code of Federal Regulations. We checked the wording against the sources linked above; code adoptions cited there reproduce the model text without amendment unless the source notes a state amendment. Codes take effect only when a state or local government adopts them, and many make amendments. This guide is general information, not legal or engineering advice. Suggest a correction