Quick answer
New septic systems, replacements and most repairs need a permit, and in most states it comes from the health department or a state environmental agency, not the building office. In Alabama, the county health department issues a Permit to Install (Repair) and an Approval for Use; in Georgia, the county health department issues the construction permit; in Texas, a county, city or other authorized agent of the Texas Commission on Environmental Quality issues on-site sewage facility permits. The usual steps are a site and soil evaluation, an approved design, an installation permit, an inspection before backfill and a final approval. Some states, including Massachusetts and Delaware, also require an inspection when the home is sold.
Who issues septic permits
EPA says “more than one in five households in the U.S. depend on individual septic (decentralized) systems” or small community cluster systems. Unlike decks or roofs, these systems are not covered by the International Residential Code’s permit process. They are regulated as a public health and groundwater matter, usually under state rules that a county health department or state environmental agency enforces.
A few state examples show how this works:
- Texas. The Texas Commission on Environmental Quality (TCEQ) sets the rules for on-site sewage facilities (OSSFs) in 30 TAC Chapter 285. Permits are usually issued by an “authorized agent,” which the rules define as a local governmental entity delegated that authority. Agents include counties, cities, river authorities and some special districts. Where no local agent exists, the TCEQ regional office issues permits, and local programs can be stricter than the state minimums.
- Alabama. The Alabama Department of Public Health’s rules say no one may “begin the installation or repair” of an onsite sewage system until a “Permit to Install (Repair)” has been issued by the local (county) health department. The system cannot be used “until an Approval for Use has been issued” (ADPH rules 420-3-1-.06 and .08).
- Georgia. No one may install a system “without having first obtained from the County Health Department a construction permit,” and it cannot be used until the county board of health has made a final inspection and issued written approval (Rule 511-3-1-.03).
- Massachusetts. Septic systems fall under Title 5 of the State Environmental Code (310 CMR 15.000), and the local board of health is the approving authority.
On a new home, the septic permit often has to be in hand before the building department will issue the building permit, so start with the health department.
How the process works
1. Site and soil evaluation
Before anyone designs a system, the soil has to be evaluated. Texas requires “a complete site evaluation” by a site evaluator or professional engineer, using “two soil borings or… two backhoe pits” (30 TAC 285.30). Georgia uses soil classifiers certified by the Department of Public Health (Rule 511-3-1-.16) and says percolation tests “may be required by the County Board of Health” (Rule 511-3-1-.07).
The evaluation looks at soil texture and structure, depth to bedrock or seasonal groundwater, slope, and flood risk. Poor results do not always rule out a lot, but they can push you from a conventional tank and drain field to an engineered system such as a mound, drip irrigation or aerobic treatment unit, which costs more to build and maintain.
2. Design and setbacks
The design sizes the tank and drain field for the home, usually by the number of bedrooms, and places it within required setbacks. Georgia, for example, does not allow an absorption field “less than one hundred feet (100’) from existing or proposed wells, springs, or sinkholes” and sets smaller distances from water lines, foundations and property lines (Rule 511-3-1-.07). Setbacks from wells, streams and lakes are often the deciding factor on small lots.
3. Installation permit
Once the design is approved, the health department or authorized agent issues the permit to install. Many states require a licensed or certified installer. Texas lets the owner of a single-family home install or repair their own system without an installer license, but “If the owner compensates a person to construct any portion of an OSSF… the individual performing the work shall be a licensed installer” (30 TAC 30.244). Local programs can be stricter.
4. Inspection and approval
The inspector checks the tank, piping and drain field before they are covered. After the system passes, you get the final approval, called an Approval for Use in Alabama and written approval after final inspection in Georgia. Keep this document and the as-built drawing: you will need them to find the system later and when you sell.
A note on large rural lots in Texas
Texas does not require planning materials, a permit or inspections for an OSSF serving a single-family home on 10 acres or more, but only if the system causes no nuisance or groundwater pollution, “all parts of the OSSF are at least 100 feet from the property line,” effluent stays on the property, and it is the only home on the tract (30 TAC 285.3). TCEQ has clarified that the construction standards still apply, and the county may still have its own requirements.
Repairs, replacements and additions
A failing drain field or a cracked tank usually needs a permit to repair. TCEQ says “A permit is required to construct, install, alter, extend, or repair an OSSF,” and lists replacing tank lids and fixing risers as examples that do not need one. For emergencies, Texas allows repairs to begin with written notice to the permitting authority within 72 hours (30 TAC 285.35). Alabama’s permit requirement covers repairs explicitly.
Changes to the house can also bring in the health department. Adding bedrooms can mean the existing system is undersized, and pools, sheds, additions, driveways and accessory dwelling units cannot be built over the tank or drain field. If your home is on septic, ask the health department whether it needs to review your building permit before you design the project. See our pool and shed guides for the building side.
Inspections when you sell
Some states require a septic inspection at sale or transfer:
- Massachusetts. A system “shall be inspected at or within two years prior to the time of transfer of title,” or up to six months after if weather prevents it, by a state-approved System Inspector (310 CMR 15.301). Transfers between close family members and into certain trusts are exempt.
- Delaware. When a property with an on-site system is sold, it must be pumped out and inspected by licensed contractors “prior to the completion of sale” (7 DE Admin. Code 7101 §5.4.6.3.1).
- Rhode Island. A cesspool serving a property that is sold must be replaced with a septic system or connected to sewer within 12 months of the sale (R.I. Gen. Laws §23-19.15-12).
Even where the state has no rule, a county ordinance, lender or buyer may ask for one. Pulling the permit file early tells you whether the system was permitted and how it was designed. Our guide to searching permit records explains how to find older files.
Keeping the system healthy
EPA’s SepticSmart program says “The average household septic system should be inspected at least every three years by a septic service professional,” and household tanks “are typically pumped every three to five years.” Systems with electrical float switches, pumps or mechanical parts should be inspected more often, generally once a year. Keep receipts: a maintenance record helps at sale and can matter if a repair permit is needed later.
What to prepare
- The lot: a survey or plat, the parcel number, and the location of any wells, springs, streams or ponds on or near the property.
- The house: number of bedrooms and the planned footprint, including driveways, garages and future additions.
- Soil or site evaluation report from the certified evaluator or engineer.
- System design stamped or signed as your state requires.
- Installer information, or proof that you qualify to install your own system where allowed.
- For repairs: the existing permit or as-built drawing and a description of the failure.
How fees work
Septic fees are set by the health department or authorized agent, not the building department, and usually cover the permit, plan review and inspections. Soil evaluation, design and installation are paid separately to the professionals who do them and are usually much larger than the permit fee. Ask for the current fee schedule when you call, and see our guide to building permit costs for the building side.
Common mistakes
- Applying to the wrong office. The building department may not issue septic permits at all.
- Designing the house first. On a tight lot, setbacks for the drain field and well can decide where the house goes.
- Covering the system before inspection. An inspector who cannot see the tank and lines can require them to be uncovered.
- Building over the drain field. Patios, driveways and sheds compact the soil and block access.
- Treating a repair as maintenance. Replacing a drain field or tank usually needs a permit; pumping and lid repairs usually do not.
- Leaving it until closing. In states with transfer inspections, a failed system can delay a sale.
Common questions
Who do I call for a septic permit?
Start with the county health department or environmental health office. In Texas, ask the county whether it is the authorized agent for on-site sewage facilities; where no local agent exists, the TCEQ regional office issues permits. In Massachusetts, the local board of health is the approving authority. Your county building office can usually tell you who handles septic where you live.
What is a perc test?
A percolation test measures how fast water soaks into the soil. Many programs now rely more on a soil evaluation, where a certified evaluator digs test pits or borings and reads the soil layers. Texas rules call for two soil borings or two backhoe pits, done by a site evaluator or professional engineer. Georgia rules say percolation tests may be required by the county board of health.
Do I need a permit to repair my septic system?
Usually. Texas rules require a permit to construct, alter, repair, extend or operate an on-site sewage facility, and Alabama requires a Permit to Install (Repair) before any repair begins. Texas lists replacing tank lids and fixing risers as work that does not need a permit, and allows emergency repairs if the permitting authority gets written notice within 72 hours.
Can I install my own septic system?
In some states. Texas lets the owner of a single-family home install or repair their own system without an installer license, but anyone paid to build part of it must be licensed, and local rules can be stricter. You still need the permit and inspections. Many other states require a licensed installer.
How often should a septic tank be pumped?
EPA says the average household system should be inspected at least every three years by a septic service professional, and household tanks are typically pumped every three to five years. Systems with pumps, float switches or other mechanical parts should be inspected more often, generally once a year.
Check your county’s rules
The rules above are a starting point. Your county, city or state agency decides which rules and code edition apply, what it changed, and what it charges. Look up the permit office that serves your address.
Sources
- U.S. EPA SepticSmart: About septic systemswww.epa.gov
- U.S. EPA SepticSmart: How to care for your septic systemwww.epa.gov
- Texas Commission on Environmental Quality: On-site sewage facility permitswww.tceq.texas.gov
- 30 Texas Administrative Code §285.2: Definitions (authorized agent)www.law.cornell.edu
- 30 Texas Administrative Code §285.3: General requirements (permits, 10-acre exemption)www.law.cornell.edu
- 30 Texas Administrative Code §285.30: Site evaluationwww.law.cornell.edu
- 30 Texas Administrative Code §285.35: Emergency repairswww.law.cornell.edu
- 30 Texas Administrative Code §30.244: Installer licensing exemptionswww.law.cornell.edu
- Alabama Administrative Code 420-3-1-.06: Permit to install (repair) an onsite sewage systemadmincode.legislature.state.al.us
- Georgia Rules 511-3-1-.03: Permits and approvals for on-site sewage management systemswww.law.cornell.edu
- Georgia Rules 511-3-1-.07: Location and setbackswww.law.cornell.edu
- Georgia Rules 511-3-1-.16: Certification of soil classifiers, contractors and inspectorswww.law.cornell.edu
- 310 CMR 15.301: Massachusetts Title 5 inspections at transfer of titlewww.law.cornell.edu
- Mass.gov: Buying or selling property with a septic systemwww.mass.gov
- 7 Delaware Administrative Code 7101 §5.0: On-site wastewater systems (inspection at property transfer)www.law.cornell.edu
- Rhode Island General Laws §23-19.15-12: Cesspools at sale or transferwebserver.rilegislature.gov
Last reviewed November 2026. Code section numbers such as R105.2 refer to the International Code Council’s model codes; CFR citations refer to the Code of Federal Regulations. We checked the wording against the sources linked above; code adoptions cited there reproduce the model text without amendment unless the source notes a state amendment. Codes take effect only when a state or local government adopts them, and many make amendments. This guide is general information, not legal or engineering advice. Suggest a correction