Quick answer
The 2024 International Residential Code exempts only two kinds of plumbing work from a permit: stopping leaks, and clearing stoppages or repairing leaks in pipes, valves or fixtures (including pulling and resetting a toilet), as long as no valves, pipes or fixtures are replaced or rearranged (IRC R105.2). Replacing a defective concealed pipe counts as new work. Repiping, adding or moving fixtures, building sewer and water service lines, and gas piping all need a permit, and the work must be tested and inspected before it is covered (P2503). Some states let owners do plumbing on their own home; others issue plumbing permits only to licensed plumbers.
What the model code says
Most U.S. jurisdictions regulate home plumbing through the plumbing chapters of the International Residential Code (IRC Chapters 25 to 33) or the International Plumbing Code. A number of states and cities use the Uniform Plumbing Code instead, and plumbing rules are amended locally more often than most trades. The section numbers below are from the 2024 IRC.
The IRC’s general permit rule covers plumbing directly. Anyone who intends to “erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system” must first apply for and get a permit (R105.1).
What is exempt
The 2024 IRC lists two plumbing exemptions (R105.2):
- “The stopping of leaks in drains, water, soil, waste or vent pipe.” There is a catch: if a concealed trap, drainpipe, water, soil, waste or vent pipe “becomes defective” and has to be replaced with new material, that is new work and needs a permit and inspection.
- “The clearing of stoppages or the repairing of leaks in pipes, valves or fixtures, and the removal and reinstallation of water closets, provided such repairs do not involve or require the replacement or rearrangement of valves, pipes or fixtures.”
The ordinary-repair allowance (R105.2.2) is narrower than many people assume. It says ordinary repairs do not include “addition to, alteration of, replacement or relocation of any water supply, sewer, drainage, drain leader, gas, soil, waste, vent or similar piping.”
Many local codes add their own exemptions. The City of Waco, Texas, for example, does not require a permit for “replacing toilets, faucets, and other fixtures in the same location without altering the pipes.” Other places require a permit even for that. Your local list controls.
Work that needs a permit
Under the model code, expect a permit for:
- Repiping. Replacing galvanized, polybutylene or failing copper supply lines with PEX or copper, in whole or in part.
- New or moved fixtures. Adding a bathroom, moving a sink to an island, adding a laundry hookup, a wet bar, an outdoor hose bib, or a dishwasher with a new drain connection. See our kitchen and bathroom remodel guide for the rest of what a remodel triggers.
- Water heaters. Replacement is not exempt. Our water heater permit guide covers the inspection.
- Building sewer and water service. The pipes running from the house to the street, the public sewer, or a septic tank.
- Gas piping. New lines for a range, dryer, fireplace, grill, pool heater or standby generator, and any alteration of existing gas piping.
- Backflow assemblies. Irrigation systems and some appliances need backflow protection. The IRC requires testable assemblies to be tested at installation and every year after (P2503.8).
Who can pull the permit
Licensing for plumbers is set by states, and some states leave room for cities to add rules. Homeowner allowances vary widely:
- Texas. “A property owner is not required to be licensed under this chapter to perform plumbing in the property owner’s homestead” (Occupations Code §1301.051). That is an exemption from licensing, not from permits. Cities that regulate plumbing require a permit before the work is done (§1301.551), and Waco, for example, issues trade permits to licensed contractors except for owners working on their own homestead.
- Massachusetts. State plumbing and gas fitting rules say “Permits shall be issued to properly licensed individuals only” (248 CMR 3.05). Homeowners hire a licensed plumber or gas fitter.
- Homeowner affidavits. Where owner permits are allowed, the office usually wants proof that you own and live in the home. East Point, Georgia, asks homeowners for a tax bill or deed plus a signed Homeowner’s Affidavit.
Gas work is sometimes treated more strictly than water and drain work, so ask about it separately. If the home is a rental or you plan to sell it soon, owner-builder rules may not apply. Our state pages summarize state licensing rules where we have researched them.
Sewer, water service and gas lines
Yard lines often involve more than one office:
- The plumbing permit covers the private piping. The IRC tests the building sewer with “not less than a 10-foot (3048 mm) head of water” held for at least 15 minutes (P2503.4).
- The sewer or water utility may issue a separate tap or connection permit. In Huntsville, Alabama, a sanitary sewer connection permit comes from the city’s Engineering Division, not the building department. In Austin, Texas, the private lateral is “the wastewater line connecting a building to the City’s wastewater system,” and work on it requires a plumbing permit.
- The health department handles septic tanks and drain fields. See our septic permit guide.
- The road department may need a right-of-way permit if the line crosses or runs under a public road. See our driveway and culvert guide.
Before any digging, contact 811, the free national before-you-dig service, so underground utilities are marked.
Permits and inspections you can expect
The IRC requires new plumbing and “parts of existing systems affected by new work or alterations” to be inspected (P2503.1), and work “shall not be covered, concealed or put into use until it has been tested, inspected and approved” (P2503.2). The permit holder supplies the test equipment and labor (P2503.3). A typical sequence is:
- Underground or underslab inspection for drains in a slab or trench, before backfill.
- Rough-in inspection before walls or ceilings are closed. Drain, waste and vent piping must pass a water test of at least a 10-foot head above the highest fitting, or an air test of 5 psi, held for 15 minutes. Plastic pipe may be vacuum-tested instead (P2503.5.1). Water supply piping is tested at not less than the system’s working pressure, or with a 50 psi air test for non-plastic pipe (P2503.7).
- Shower liner test where a site-built shower pan is used: the liner is filled to at least 2 inches at the threshold for at least 15 minutes (P2503.6).
- Gas piping test before the piping is covered and before the meter is set or the appliance is connected (G2417). The inspector checks the test gauge against the required pressure and time.
- Final inspection once fixtures are set and working (P2503.5.2).
Leave test plugs and gauges in place until the inspector has signed off, and keep the permit card posted where the inspector can find it.
What to prepare
- A fixture list with each fixture new, moved or replaced, since fees are often counted per fixture.
- A simple riser or floor plan for repipes and new bathrooms, showing pipe material, sizes, drain and vent routing, and where the new lines tie in.
- Gas appliance details: input ratings in BTU per hour and the length of each run, which set pipe size.
- Sewer or water service details: the length of the new line, material, and the connection point.
- License information for your plumber, or proof of ownership and occupancy for a homeowner permit.
How permit fees are calculated
Plumbing fees are usually a base or issuing fee plus a charge per fixture, with separate line items for water heaters, yard lines and gas piping. Three published schedules show the range:
- East Point, Georgia (May 2026 form): a $75 base fee plus fixture fees. Most fixtures, including toilets, sinks, showers, tubs, dishwashers, washing machines and sillcocks, are $2.50 each. A water heater is $20, and sewer and water service lines are $0.10 per foot. Gas piping is priced by capacity in cubic feet. Replacing a toilet, vanity sink and tub there would come to $75 plus 3 × $2.50, or $82.50.
- Waco, Texas: $8 for each plumbing fixture, trap, water heater or gas appliance, and $20 per 100 feet for each sewer, water or gas yard line, plus a technology fee. Reinspection fees rise with each failed inspection.
- Auburn, Alabama: a $10 issuing fee, $2.50 per fixture, floor drain or trap, and $5 for each house sewer.
Some cities fold plumbing into a single valuation-based building permit for remodels. Our guide to building permit costs explains the methods, and your county’s profile in our directory links to its fee schedule.
Common mistakes
- Treating a pipe replacement as a repair. Fixing a leak is exempt; cutting out and replacing a defective section of concealed pipe is new work.
- Closing walls before the rough-in. An inspector who cannot see the piping can require you to open the wall.
- Skipping the test. Pipes that “look fine” are not the standard. The inspection is based on a water, air or pressure test held for a set time.
- Assuming a licensing exemption covers the permit. In Texas, for example, a homestead owner may not need a license but still needs a city permit where the city requires one.
- Forgetting the utility. A new sewer or water connection can need a tap permit and fee from the utility, separate from the plumbing permit.
- Doing gas work without asking. Gas piping usually has its own test and sometimes its own permit and licensing rules.
- Leaving work unpermitted. Unpermitted plumbing can come up at a sale or after an insurance claim. Our guide to unpermitted work explains the options for getting it legalized.
Common questions
Do I need a permit to replace a faucet or toilet?
The model IRC exempts removing and reinstalling a toilet and repairing leaks, but not replacing fixtures. Many cities exempt like-for-like swaps anyway. The City of Waco, Texas, for example, lists replacing toilets, faucets and other fixtures in the same location without altering the pipes as work that does not need a permit. Check your local list before assuming either way.
Can a homeowner pull their own plumbing permit?
It depends on the state and the city. Texas law says a property owner does not need a plumbing license to do plumbing in their own homestead, though cities that regulate plumbing still require a permit. Massachusetts plumbing rules say permits are issued only to properly licensed individuals. Where homeowner permits exist, offices usually ask for proof of ownership and a signed homeowner affidavit.
Does replacing a sewer line need a permit?
Yes, under the model code. Replacing or relocating sewer, drainage or water supply piping is excluded from the ordinary-repair allowance (IRC R105.2.2), and the building sewer has its own test (P2503.4). A new connection to a public sewer may also need a separate tap or connection permit from the sewer utility.
What is a rough-in plumbing inspection?
It is the inspection of drain, waste, vent and water piping after it is installed but before walls, floors or ceilings close it in. The 2024 IRC requires drain and vent piping to pass a water test (a 10-foot head) or an air test (5 psi), held for 15 minutes, and water supply piping to pass a test at working pressure (P2503.5, P2503.7).
Do I need a permit to run a gas line for a stove, dryer or generator?
Yes. Adding or altering gas piping is not an ordinary repair under the IRC. Gas piping must be inspected and pressure-tested before it is covered or put into service (IRC Section G2417). Some places handle gas under the plumbing permit, others under a separate gas or mechanical permit.
Check your county’s rules
The rules above are a starting point. Your county, city or state agency decides which rules and code edition apply, what it changed, and what it charges. Look up the permit office that serves your address.
Sources
- 2024 International Residential Code, Chapter 1 (R105.1 permits required, R105.2 exemptions, R105.2.2 repairs), unamended adoption reproduced by UpCodesup.codes
- 2024 International Residential Code, Chapter 25 (P2503 inspections and tests)up.codes
- 2024 International Residential Code, Chapter 24 (fuel gas: G2415 piping installation, G2417 inspection, testing and purging)up.codes
- Texas Occupations Code §1301.051: Plumbing by property owner in homesteadtexas.public.law
- Texas Occupations Code §1301.551: Municipal ordinances and permitstexas.public.law
- 248 CMR 3.05: Massachusetts plumbing and gas fitting permits (Cornell LII)www.law.cornell.edu
- City of East Point, Georgia: Plumbing permit application and fee sheet (updated May 2026)eastpointga.gov
- City of Waco, Texas: Inspection Services fee scheduleswww.waco-texas.com
- City of Waco, Texas: Do I need a permit?www.waco-texas.com
- City of Auburn, Alabama: Inspection Services permit feeswww.auburnal.gov
- City of Huntsville, Alabama: Sewer connection permitwww.huntsvilleal.gov
- City of Austin, Texas: Private lateral programwww.austintexas.gov
- 811 Before You Dig (Common Ground Alliance)811beforeyoudig.com
Last reviewed November 2026. Code section numbers such as R105.2 refer to the International Code Council’s model codes; CFR citations refer to the Code of Federal Regulations. We checked the wording against the sources linked above; code adoptions cited there reproduce the model text without amendment unless the source notes a state amendment. Codes take effect only when a state or local government adopts them, and many make amendments. This guide is general information, not legal or engineering advice. Suggest a correction