Under the 2024 International Residential Code, stationary generators must be listed to UL 2200, and their connection to house wiring "shall be by means of a listed transfer switch" (R331.1). They must be installed in an approved location following the listing, the manufacturer's instructions, and the electrical chapters (R331.2). A natural gas or propane unit also needs a fuel gas permit, with piping sized for its full input (G2413). EV charging systems "shall be installed in accordance with NFPA 70" (the National Electrical Code, Article 625), with chargers listed to UL 2202 and supply equipment to UL 2594 (R317.6). Chargers rated above 16 amps or 120 volts need their own branch circuit, and their load counts as continuous (E3702.14). Plugging a car into an existing outlet needs no permit. A new 240-volt circuit or hardwired charger does.

Standby generators

A standby generator is a permanently installed engine generator, usually on a pad outside the house, fueled by natural gas, propane, or diesel. It starts when utility power fails and feeds some or all of the house through a transfer switch. Three permits are common: electrical, fuel gas, and sometimes a building or zoning review of the location.

What the model code says

The 2024 International Residential Code has a short section on generators (R331):

Stationary engine generators shall be listed and labeled in accordance with UL 2200 and shall comply with this section. The connection of stationary engine generators to the premise wiring system shall be by means of a listed transfer switch.

The installation “shall be in an approved location and in accordance with the listing, the manufacturer’s installation instructions and Chapters 34 through 43” (R331.2). The detailed wiring rules come from the National Electrical Code (NFPA 70). A home standby system that isn’t legally required is an optional standby system under NEC Article 702. The NEC edition in force varies by state and city. Massachusetts, for example, moved to the 2026 NEC on April 24, 2026. Ask your permit office which edition applies.

The transfer switch isolates the house from the utility while the generator runs. Without one, a generator can backfeed the utility lines and energize wires that line workers expect to be dead. Under Article 702, a generator connected through an automatic transfer switch must be able to carry the full load the switch can transfer, unless a load management system limits what the generator picks up. Your electrician’s sizing should show which of these approaches the design uses.

Gas and fuel permits

A natural gas or propane generator is a gas appliance, and new gas piping needs a permit. The IRC’s exemptions for gas cover only portable appliances and minor part replacements (R105.2). Two things to know:

  • Pipe sizing. Gas piping must supply “the maximum demand,” based on “the total connected hourly load,” assuming “all appliances could be operating at full capacity simultaneously” (G2413.1, G2413.2). A whole-house generator can use more gas than the rest of the house combined, so the existing pipe, meter, or regulator may be too small. Ask your gas utility early whether it needs to upgrade the meter.
  • Testing. New piping must be “visually inspected and pressure tested” before it goes into service (G2417.1).

Propane tanks bring their own placement rules from the fire code and the propane supplier, including distances from buildings, property lines, and ignition sources.

Location and noise

Your permit office will check the pad location against:

  • the manufacturer’s clearances from windows, doors, vents, and combustible walls, which keep exhaust out of the house;
  • zoning setbacks and any rules about equipment in side or front yards;
  • local noise limits, and sometimes rules on when the weekly test cycle may run;
  • flood elevation, if you’re in a mapped flood zone.

HOAs may regulate placement. Texas limits that power for permanently installed standby generators. An HOA there may not prohibit them, but may require “all electrical, plumbing, and fuel line connections to be installed only by licensed contractors,” regulate location and screening, and set testing times (Texas Property Code §202.019).

Portable generators don’t need a permit when you run appliances on extension cords. Connecting one to house wiring through an inlet and interlock or transfer switch is electrical work that needs a permit. See our electrical permit guide.

Home EV chargers

Level 1 charging uses the cord that comes with the car, plugged into an ordinary 120-volt receptacle. If the receptacle already exists, there’s no new wiring to permit, though a dedicated circuit is better. Level 2 charging runs at 240 volts. It needs a new circuit to a receptacle or a hardwired charger, and that needs an electrical permit.

What the model code says

The 2024 IRC puts EV charging in the garage section (R317.6):

Where provided, electric vehicle charging systems shall be installed in accordance with NFPA 70. Electric vehicle charging system equipment shall be listed and labeled in accordance with UL 2202. Electric vehicle supply equipment shall be listed and labeled in accordance with UL 2594.

The IRC’s electrical chapters pick up the core NEC Article 625 rules:

  • Its own circuit. “Each outlet installed for the purpose of supplying electric vehicle supply equipment greater than 16 amperes or 120 volts shall be supplied by an individual branch circuit” (E3702.14, from NEC 625.40).
  • Continuous load. “Electric vehicle charging loads shall be considered to be continuous loads” (E3702.14, from NEC 625.42). Conductors for continuous loads must be sized at 125 percent of the load (E3701.2.1). A charger set to draw 48 amps needs a 60-amp circuit, and one set to 40 amps needs a 50-amp circuit.
  • Load calculation. The IRC’s feeder load calculation counts EV supply equipment at “7,200 watts (volt-amperes) or the nameplate rating of the equipment, whichever is greater” (Table E3704.2(1)). On a 100-amp or older 150-amp service, adding a charger can push the calculated load over the limit. The usual fixes are a smaller charger setting, a load management device, or a service upgrade.
  • GFCI. Receptacles in garages and outdoors need ground-fault protection under the IRC’s GFCI rules (E3902), and the NEC edition your jurisdiction uses may add EV-specific requirements.

The 2024 IECC, reproduced in the IRC as Appendix NE (RE), includes optional EV-ready requirements for new homes. They apply only where your jurisdiction adopts them. If you’re building a garage or addition, ask whether a circuit or conduit for a future charger is required, or simply worth adding while the walls are open. See our home addition and garage guide.

Utility notification and service capacity

Your utility may need to know about both kinds of equipment:

  • Generators. Ask your utility whether it wants to be told about a permanent standby generator. The transfer switch is what actually protects line workers.
  • EV chargers and service upgrades. A large new load can require a bigger service drop, meter, or transformer, which only the utility can provide. Ask about EV rate plans and managed-charging programs too. Some require a compatible charger, as Austin Energy’s rebate does.
  • Energizing new work. Some states bar utilities from connecting new electrical work until it has a permit. Montana’s law says power suppliers “may not connect with or energize an electrical installation” unless the owner or a licensed electrical contractor has delivered an electrical permit, apart from limited temporary connections (MCA 50-60-605).

Rebates and tax credits

Check incentive rules before you buy equipment, because many programs set conditions on the equipment, the installer, or the paperwork:

  • The federal credit has ended. The IRS says the Section 30C credit for home charging equipment applied to property placed in service “from January 1, 2023, to June 30, 2026.” Chargers installed after that date don’t qualify.
  • Utility rebates. Austin Energy’s home charging rebate pays “up to $500 or 50% of your purchase price” for a Level 2 charger compatible with its Power Partner program. It requires installation “in accordance with all applicable federal, state, and local laws” and makes the customer or installer responsible for permitting and inspection. SMUD’s Charge@Home program offers “up to $850 toward EV charging equipment and installation costs.”
  • Proof of permit. Programs that ask for an electrician’s invoice, a permit number, or a final inspection record are easy to satisfy if you pulled the permit, and hard to satisfy after the fact if you didn’t.

HOA rules on chargers are limited in some states. California Civil Code §4745 voids HOA rules that “effectively prohibits or unreasonably restricts the installation or use of an electric vehicle charging station,” while letting the HOA require a licensed contractor and liability insurance for stations in common areas.

Permits and inspections you can expect

Standby generator:

  1. Zoning or site review of the pad location, if your jurisdiction requires it.
  2. Electrical permit for the transfer switch, generator wiring, and any panel changes.
  3. Gas permit for new piping or a propane tank, with a pressure test and inspection.
  4. Final electrical and gas inspections. Then the installer starts the generator and tests the transfer switch.

EV charger:

  1. Electrical permit, often with a load calculation for the existing service.
  2. Rough-in inspection, if wiring will be concealed in walls.
  3. Final inspection of the circuit, receptacle or hardwired charger, and labeling.
  4. Utility coordination if the service is being upgraded.

What to prepare

  • Equipment specification sheets showing the UL 2200 generator listing, or the UL 2202 or UL 2594 charger listing, and the manufacturer’s installation instructions.
  • A load calculation for the existing service, and the generator sizing or load management plan.
  • A site plan showing the generator pad, clearances to openings and property lines, the gas meter, and any propane tank.
  • Gas pipe sizing, with pipe lengths and the input ratings of all gas appliances.
  • The transfer switch type (automatic or manual, whole-house or selected circuits), or the charger’s amperage setting.
  • HOA approval, if covenants apply.

Common mistakes

  • Backfeeding a portable generator through a dryer outlet with a double-male cord. It can energize the utility lines and is never allowed.
  • Undersized gas piping or meter, which makes the generator stall under load.
  • Setting the generator too close to windows, doors, or vents.
  • Putting a charger on a shared circuit or sizing the breaker at 100 percent of the charger’s draw instead of 125 percent.
  • Skipping the load calculation on an older service.
  • Buying equipment before reading rebate terms, then finding the charger or installer doesn’t qualify.

Adding solar or batteries too? See our rooftop solar guide. Find your local permit office in our state directory.

Common questions

Do I need a permit to install a whole-house standby generator?

Yes, nearly everywhere. Expect an electrical permit for the transfer switch and wiring, a gas or fuel permit for the natural gas line or propane tank, and often a building or zoning review of the pad location. The 2024 IRC requires a listed transfer switch for every stationary generator connection (R331.1).

Do I need a permit for a Level 2 EV charger?

Yes, if it needs a new 240-volt circuit, a new receptacle, or hardwiring. That is new electrical work. A Level 1 charger plugged into an existing 120-volt outlet doesn't involve new wiring. The 2024 IRC requires an individual branch circuit for chargers rated above 16 amps or 120 volts (E3702.14).

How big a circuit does an EV charger need?

The IRC treats EV charging as a continuous load (E3702.14), and conductors for continuous loads must be sized at 125 percent of the load (E3701.2.1). A charger that draws 40 amps continuously therefore needs at least a 50-amp circuit. Follow the charger's installation manual and your electrician's load calculation.

Do I have to tell the utility about a generator or EV charger?

Often, yes. A transfer switch keeps a generator from sending power back into utility lines, but your utility may still want to know about a permanent generator. A large new load such as a charger may need a bigger service or transformer. Some states bar utilities from energizing new electrical work until it has a permit. Montana's law is one example.

Can my HOA stop me from installing a generator or charger?

Some states limit HOA restrictions. Texas Property Code §202.019 bars HOAs from prohibiting permanently installed standby generators, though it allows rules on location, screening, licensed installation, and testing times. California Civil Code §4745 voids HOA rules that effectively prohibit or unreasonably restrict EV charging stations.

Check your county’s rules

The rules above are a starting point. Your county, city or state agency decides which rules and code edition apply, what it changed, and what it charges. Look up the permit office that serves your address.

Sources

Last reviewed November 2026. Code section numbers such as R105.2 refer to the International Code Council’s model codes; CFR citations refer to the Code of Federal Regulations. We checked the wording against the sources linked above; code adoptions cited there reproduce the model text without amendment unless the source notes a state amendment. Codes take effect only when a state or local government adopts them, and many make amendments. This guide is general information, not legal or engineering advice. Suggest a correction