Colorado building permits

Colorado has no single statewide building code for houses. Cities, towns and counties each decide whether to adopt and enforce building codes, so requirements, and whether a permit is needed at all, depend on where the property is. The state does set statewide minimum codes for electrical and plumbing work. The State Electrical Board and State Plumbing Board license those trades and issue permits and inspect work where no local government does. Since August 1, 2026, the state electrical code is the 2026 National Electrical Code.

Local profiles
64
Link an online portal
38 (59%)
County office
60
City or town offices
3
State agency
1

How permits work in Colorado

Building codes

Partial statewide code

There is no statewide building or residential code for one- and two-family homes; local governments adopt their own. Two state boards set statewide minimum trade codes. The State Electrical Board's rules adopt the 2026 National Electrical Code as the minimum standard for electrical work throughout Colorado, effective August 1, 2026 (it replaced the 2023 NEC). The State Plumbing Board's rules create the Colorado Plumbing Code and Colorado Fuel Gas Code from the 2024 International Plumbing Code, the 2024 International Fuel Gas Code and the plumbing and gas chapters of the 2024 International Residential Code, with Colorado amendments. For hotels, motels and multi-family buildings in areas with no local building department, and for factory-built (modular) structures and tiny homes, the Division of Housing applies the 2024 International Building Code and 2024 International Residential Code with state amendments.

Department of Regulatory Agencies, Division of Professions and Occupations (State Electrical Board and State Plumbing Board); Department of Local Affairs, Division of Housing

Outside city limits

Whether you need a building permit outside town limits depends on the county. Some counties run a building department and enforce adopted codes in unincorporated areas, and others have none. Electrical and plumbing permits are still needed statewide, though. Where the county does not handle them, the State Electrical Board and State Plumbing Board issue the permits and inspect. Some counties have taken this over: since July 1, 2020, electrical permits in unincorporated Larimer County come from the county building division instead of the state. Where there is no local building department, the state Division of Housing reviews hotels, motels and multi-family buildings and issues their certificates of occupancy.

Contractors and owner-builders

Colorado does not license general contractors, remodelers or roofers at the state level. Many cities and counties have their own contractor licensing or registration, so check with the local building department. Electrical and plumbing contractors must register with their state boards, and individual electricians (master, journeyman, residential wireman) and plumbers (master, journeyworker, residential) must hold state licenses. Only a registered contractor or a homeowner working on their own home may take out an electrical or plumbing permit, and a contractor may not work under a homeowner's permit. Homeowners may do electrical work only on the home they live in, and only if the property is not for sale, resale, rent, short-term rental or other commercial use. Local governments may add their own conditions for homeowner permits.

Department of Regulatory Agencies, Division of Professions and Occupations · Look up a license

Electrical, plumbing, and HVAC

The State Electrical Board licenses master electricians, journeyman electricians and residential wiremen, registers electrical contractors and photovoltaic installers, and adopts the National Electrical Code (2026 edition since August 1, 2026). A wiring permit is required for systems that supply power normally supplied by a utility, such as solar, wind or other generators. The State Plumbing Board licenses master, journeyworker and residential plumbers, registers plumbing contractors and apprentices, and adopts the Colorado Plumbing and Fuel Gas Codes. Permits for plumbing, fuel gas piping, water conditioning equipment and manufactured home hookups come from the state board or from the local authority having jurisdiction. After emergency plumbing such as a broken water line or a water heater replacement, the permit may be pulled the next business day. Work started before a permit is bought is charged double the permit fee. The state does not license HVAC work; check local requirements.

State programs that can affect your permit

  • State electrical and plumbing permits and inspections

    Where a city or county does not do its own electrical or plumbing inspections, permits are bought from, and inspected by, the State Electrical Board or State Plumbing Board. Homeowners doing their own work can be the permit holder. Inspection requests are accepted only from the permit holder or their agent.

  • Division of Housing: factory-built structures, tiny homes and buildings in areas with no building department

    The Department of Local Affairs, Division of Housing, regulates factory-built residential and commercial (modular) structures, manufactured home and tiny home sellers and installations. In areas of Colorado with no building department, it also covers hotels, motels and multi-family structures. Modular homes must sit on a permanent foundation. Where no building codes have been adopted, the foundation must be designed by a Colorado-licensed engineer unless the plans are approved by the Division and follow its adopted IRC prescriptive foundation rules.

  • On-site wastewater (septic) permits

    Septic systems with a design capacity of 2,000 gallons per day or less are permitted under regulations adopted by local boards of health under state Regulation 43. A building permit for a structure with plumbing that is not served by a sewer cannot be issued until the local public health agency has issued the septic (OWTS) permit. An occupancy permit cannot be issued until that agency has done a final inspection and approved the installation.

  • Accessory dwelling units (HB24-1152)

    Since June 30, 2025, 'subject jurisdictions' must allow one ADU as an accessory use wherever single-unit detached homes are allowed, with only administrative approval. Subject jurisdictions are municipalities of 1,000 or more people in a metropolitan planning organization area, and the parts of counties in census designated places of 40,000 or more within such an area.

Colorado county directory

64 local profiles

Portal links an online permit portal (38). Fees links a fee schedule (52). Profiles that point to a city, town or state agency are labeled.

Profiles marked “City or town offices” point to municipal permit offices because the county does not issue general building permits. Profiles marked “State agency” point to a state program that handles permits or oversight there.

Statewide rules for common projects

  • Electrical work

    The 2026 National Electrical Code is the statewide minimum standard for electrical work from August 1, 2026. Permits are issued to a registered electrical contractor or to a homeowner doing their own work, and a contractor may not work under a homeowner's permit.

    Official source · Electrical work permit guide

  • Rooftop solar

    State Electrical Board rules require a permit for any system that supplies power normally supplied by an electric utility, including solar. Photovoltaic installers register with the Board and pull permits in their own name.

    Official source · Rooftop solar permit guide

  • Water heaters

    Under the Colorado Plumbing Code, emergency plumbing work such as a water heater replacement or a broken water or drain line may start before the permit is bought, provided the permit is obtained the next business day.

    Official source · Water heaters permit guide

  • Accessory dwelling units

    Under HB24-1152, since June 30, 2025, subject jurisdictions (municipalities of 1,000 or more in a metropolitan planning organization area, and county areas within large census designated places in such an area) must allow one ADU wherever single-unit detached homes are allowed, through administrative approval only.

    Official source · Accessory dwelling units permit guide

Colorado permit questions

Does Colorado have a statewide building code?

Not for houses in general. Each city, town and county decides which building codes to adopt, or whether to adopt any. Electrical and plumbing are the exceptions. The 2026 National Electrical Code (effective August 1, 2026) and the Colorado Plumbing and Fuel Gas Codes, based on the 2024 International Codes, apply statewide as minimum standards.

Can I do my own electrical work in Colorado?

Yes, on the home you live in, as long as the property is not for sale, resale, rent, short-term rental or other commercial use, and you get a permit and inspections. A contractor cannot work under your homeowner permit. Local governments can add conditions. Denver, for example, issues homeowner permits only for single-family homes, requires you to pass an exam before doing electrical, plumbing or mechanical work, and requires you to live in the home for at least a year after the work is done.

Do I need a state contractor license to remodel or build in Colorado?

No state license exists for general contractors, remodelers or roofers. Many cities and counties license or register contractors locally, so check with the local building department. Electrical and plumbing work needs state-licensed tradespeople and a registered contractor (unless a homeowner is doing their own qualifying work).

Who issues permits if my county has no building department?

For general construction, there may be no building permit at all, but zoning, septic and other county rules still apply. Electrical and plumbing permits still come from the State Electrical Board and State Plumbing Board. Septic permits come from the local public health agency, and hotels, motels and multi-family buildings go through the state Division of Housing.

Permit guides for common projects

What the model codes say, what local offices often change and what to ask; read them with the Colorado rules above.

Sources

Last verified October 28, 2026. State rules change. The issuing agency’s current instructions control if they differ from this summary. Suggest a correction